Plant capacity at start of operations
|
425,000 cubic meters per day = 93.5 million imperial gallons per day |
 |
Plant capacity after expansion |
600,000 cubic meters per day = 132 million imperial gallons per day |
 |
Ardiya site area |
60,000 square meters |
 |
Sulaibiya site area |
110,000 square meters |
 |
Three transfer pipelines (Ardiya-Sulaibiya) |
| |
|
Diameter of each |
1400 m |
 |
Length of each |
25 km |
 |
Concession period |
30 years - began 7th July 2002 |
 |
EPC turnkey contract duration |
29 months - began on 7th July 2002 |
 |
Operations and maintenance period |
Up to year 2032 |
 |
Working man-hours for EPC works |
7,000,000 man-hours |
 |
Date of commercial operation commenced |
1st December 2004 |
| |
|
| |
|